Project Update - July 2018

Published on 25 July 2018

The tender phase and final is now complete and works have been scheduled.

Starting from next week (30 July 2018) the area of works will be fenced off as part of the setup process. The following week (6 August 2018) works will commence. The majority of these works will occur between the hours of 7.00am and 6.00pm Monday to Saturday (excluding public holidays), with some earlier starts for large concrete works.

These works are expected to be completed in late March 2019, weather permitting. During the works a section of Meadowbank Park will be closed. The remainder of the park will remain open.

We apologise for any inconvenience these works may cause and thank you for your patience. For more details about these works click here(PDF, 620KB) to view the notification flyer.