ELS Hall Park Playground Upgrade

  • Project typePlayground Upgrade
  • Project value$644,000
  • Project StatusCompleted
ELS-Hall-Park-Playground-Upgrade_SQ.jpg

The West Ryde Plaza Embellishment project is part of the City of Ryde's Four Year Delivery Plan (2016-2020) to create more inviting and activated public spaces in our Neighbourhood and Town Centres.

Works will be carried out in two stages.

Stage 1 - Completed
  • New play space for kids
  • Additional trees and seating
  • New Concrete planters
Stage 2
  • Installation of the shade structure
  • Wi-Fi, CCTV and lighting
Timing and Nature of Works
  1. Construction is on schedule for completion in April 2019 (Weather permitting) 
  2. Future works involve installation of a new shade structure, Wi-Fi, CCTV and lighting for completion in June 2019 (weather permitting)
  3. Work hours are Monday to Saturday 6:30 am - 5 pm (weather permitting and excluding public holidays)

Every effort will be made to minimise the impact of the works on residents and businesses and property access will be maintained continuously during construction. 

Location

Kent Road, North Ryde 2113  View Map