Project Update - Westminster Park Masterplan Concept Design
Published on 21 May 2021
Concept Design - Phase 1 Upgrades
The concept design for Phase 1 of the Westminster Park Masterplan delivery has now been finalised. The following park upgrades are identified for delivery in two stages over the coming years:
Phase 1A Upgrade:
- Natural turf sportsground renewal
This upgrade is scheduled to commence in September/October 2021. A separate notification containing detailed project information will be sent prior to these works commencing.
Phase 1B Upgrades:
- Access improvements from Westminster Road to the sportsground
- Terraced seating area adjacent to amenities building
- Increased seating opportunities around the park
- New connection from Ryde Road to sportsground
- Additional tree planting to increase tree canopy
These upgrades are scheduled to be delivered as funding becomes available.
View the Phase 1 Concept Design(PDF, 12MB)
Phase 2 Upgrades
Phase 2 upgrades that are due to occur but have not yet been scheduled for delivery include:
- Stormwater mitigation works
- Conversion of the natural turf sportsground to a synthetic surface
- Upgrade of the park amenities and community building
Once funding has been allocated for the design and delivery of these upgrades, Council will provide a further update.
🔗Click here to read the full project update